Simulate transfer of Risk and Compliance data
You can simulate the transfer of data from ARIS to ARIS Risk and Compliance in order to verify whether the changes that would occur due to the transfer are correct and executed without errors.
Prerequisite
You have the Risk and Compliance administrator or the Risk and Compliance data transfer manager function privilege.
You have the Risk and Compliance (Operate) license privileges.
You have the ARIS Designer or ARIS Architect license privilege.
The ARIS database used for this transfer must be the one specified for the environment in ARIS Administration (Configuration > Risk and Compliance > DATA MANAGEMENT > Environments).
Start ARIS Architect.
Click ARIS >
Explorer. The Explorer tab opens.Click
Navigation in the bar panel if the Navigation bar is not activated yet.Navigate to the relevant database in ARIS Architect and log in to the database.
Select the item from which you want to start the transfer.
Activate the Contents tab bar.
Click Export > Transfer Risk and Compliance data. The corresponding dialog opens.
Select the environment to which the data is to be transferred. If no environment is displayed or if you want to use another environment than the one displayed, you must specify the database in the respective environment in ARIS Administration (Configuration > Risk and Compliance > DATA MANAGEMENT > Environments).
Enable Simulate transfer.
Enable Activate transfer report to generate a file that contains transfer or simulation details, such as objects that have not been updated. If you enabled the option, you must specify the file location. Otherwise, you cannot start the report.
Click OK.
The simulation is performed and the log file is displayed. If errors occurred, resolve them.
Now you can start the transfer of data from ARIS to ARIS Risk and Compliance.