Generate follow-ups
You can generate follow-ups for control tests. Optionally, the generation of new control tests can be suspended until the follow-up of the previous control test is finished (
Administration > General > System management > System configuration > Basic settings > Application > Suspend generation of control tests during follow-up. Otherwise, control tests are automatically generated at the points in time specified in parallel with the follow-up.
Prerequisite
You have the Control test manager role.
Follow-ups can be generated for the following control tests:
- For control tests that were not tested and were closed automatically by the system.
- For control tests that could not be executed.
- For control tests whose controls were not effective and for which there is no deficiency and no issue.
Click
Administration > Server tasks.Under Test Management > Generate follow-ups, click Generate.
The list of control tests you can generate follow-ups for is displayed.
In the row for the control test for which you want to generate a follow-up, click
Generate follow-ups. Alternatively, enable (
) multiple control tests and click
Generate follow-ups. The corresponding dialog opens.Enter the start date and the duration of the testing period in days.
Click Execute.
The dialog closes.
Administration > Monitoring > Functional > Server tasks is displayed. The server task is displayed under Server tasks in progress. When complete, the server task is listed under Completed server tasks (last 10). If follow-ups were generated, the roles responsible are informed that new follow-ups are available for editing. You can check the generated follow-ups in Explorer under Test Management.